| Background | |
For decades Denmark has been supplied with electricity via the State electricity grid, generated by coal and
gas-fired power stations more than 400km away. Being near the end of such a long transmission line,
Denmark continues to experience power quality and reliability issues, including occasional extended
blackouts in some areas. Population growth and more appliances being connected means that the need
for a more reliable supply has reached a critical level. |
![]() |
An aerial view of Wilson head, looking southwest. The imposed WEF zone and turbines indicate approximately where the windfarm will be in relation to the surrounding area. (Click to enlarge). |
| The Proposal | |
The Denmark community windfarm project is the first of its kind in Australia. It is a $3m project, owned and operated by the Denmark community through an incorporated association, Denmark Community Windfarm Inc (DCW). It is proposed to erect two 800kW Enercon E48 wind turbines with a total installed capacity of 1.6MW on a small section of a disturbed coastal reserve, south of an existing limesand quarry at Wilson Head, Denmark (see map). Electricity will be generated into the Western Power grid. GHD, a leading Perth civil engineering firm, completed the project’s feasibility study, which shows the project to be technically feasible and financially viable. |
|
| 7 December 2005: DCW Chairman Craig Chappelle, left, signing the contract employing international engineering firm, GHD Pty Ltd, to do a final feasibility study of the windfarm proposal. GHD's Perth manager, Jim Gooding, is on the right. | ![]() |
| The Site | |
![]() |
AN aerial photomontage of the site, looking south east. The turbines will be located on the right, behind the limesand quarry. Note the existing extensive man-made impacts |
A survey of the district conducted by SkyFarming in 2003-4 identified eight potential sites for a windfarm. Each was evaluated against
a set of established criteria, resulting in Wilson Head becoming the preferred site, because it best met all
the criteria and was most likely to deliver a viable project. (Note: there is no 'alternative site' for a Denmark windfarm: even though DCW recommended that all suitable sites identified in its survey be retained as additional potential sites, council's Draft Local Planning Strategy identifies only one - the current site at Wilson Head.) |
|
| Who will own the Windfarm | |
The project has always, and will continue to belong to the Denmark community. DCW is a registered not-for-profit community group which currently manages the project on behalf of its members and the broader
community, through an elected committee of local residents, who have so far given more than 10,000
hours of voluntary time to make the windfarm a reality. This way a community-based control mechanism will continue to oversee the distribution of profits, as required by DCW's constitution: that the windfarm be owned and operated by the community. This ensures that all Denmark residents will benefit - either directly, through holding shares in DPC; or indirectly, through a community "future fund" which will provide financial assistance for community projects such as sporting and cultural facilities, programs for youth and the aged and so on. Best of all, everyone in Denmark, shareholder or not, will have direct access to their own source of clean, greeen energy. |
|
| Current Status | |
| The project's final feasibility stage is complete, and the design and final planning phase is ready to commence, once the final State planning requirements are achieved. Construction and installation are slated for completion in 2009, with commissioning of the windfarm scheduled for mid 2011. Current funding will cover the design and planning phases. Capital for construction, installation and operation will be sought either through single sponsorship or issue of a prospectus, probably in the first half of 2009. An application for federal funding to cover 50% of infrastructure costs was successful in receiving approval from the state and federal governments. |
|
| Next Steps | |
The windfarm will play a major role in solving Denmark’s historic energy problems. It may also become the
beating heart of an exciting energy storage project currently being investigated by Western Power, to
overcome transmission losses and balance load variations when the wind isn’t blowing. |
| This project received funding from the federal government's former Regional Partnership programme, through the WA Sustainable Energy Development Office (SEDO) |
Home | About Us | The Project | FAQ | Membership | Photos | Links | Contact Us |